After 90 days, DLP finished the construction of SúperBodega aCuenta in Maipú.

September 2010. More than 120 workers participated in the construction of SúperBodega aCuenta in Maipú; D&S company´s ownership.

The work was constructed in a 2.100 square meters surface, and it was built with a metal structure, coated with panels of the same material and mineral wool insulation lined with a PVC panel. The project integrates interior spaces for the selling of the products, as well as a dining hall for its employees, storehouses, access control offices, cold storage rooms, and bathrooms. In addition, the work also includes two parking lots; one of 1.500 square meters, built over asphalt surface, and the other one of 500 square meters destined to trucks.

SúperBodega aCuenta was constructed in 90 days, been finished on the 14th of April, adding up to the other 14 retail stores built by Constructora DLP.